Apr 01, 2023     27-3 thru 27-5: Tunnel assembly - (6.0 hours)       Category: 27: Firewall
Prepped and primed the tunnel ribs and attachment angles.

Startedtes clecoing to the firewall and realized I had made a mistake last week. I riveted the rudder pedal support brace to the firewall inset. I was supposed to rivet the tunnel attachment angle at the same time and put the rudder pedal brace on the outside. I had counter sunk the rudder support brace to receive the inset dimples. That's a problem. Ordered a new rudder support brace.

Proceeded with clecoing everything up and installed the scat tube support and installed all of the #8 nut plates on the tunnel ribs.

4/2: riveted the nose wheel attach brackets to the ribs. Then riveted the rib assembly lies to the firewall. Everything is done except the rudder brace. I don't know how I'm going to get those rivets in.

4/8: received my replacement rudder bracket and primed it along with some other fuselage parts. Installed using five cherry max rivets.

This section is done.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.